Taxilanes G & L Widening, Phase 1

Overview

The Taxilanes G & L widening project primarily consists of pavement reconstruction and overlay of portions of Taxilanes G & L and Taxiway A. Additional work include demolition and reconstruction of airfield lighting and signage, construction of new storm drain systems, and extension of the box culvert to cover a portion of the Manuwai Canal near Taxiway A to meet FAA design and safety standards.

Current Phase Work Area

The current active working area is Phase1-F. 

Prior to the commencement of each phase, a Pre-Phase meeting will be held to provide information to airport stakeholders that will assist in their preparation for the upcoming construction work. The agenda will briefly cover scope of work, operational impacts, phase start time & duration, contractor haul routes, aircraft routing and ARFF/EMS access. Minutes for the pre-phase meeting for Phases 1-F and 1-G may be viewed here.  

 

The following will be updated on a regular basis and can be viewed by clicking on the respective links:

  • Weekly project meeting minutes for the current phase.
  • Outage request, including GSE road closures, for the current working area.
  • Phase 1-F schedule.
 
Upcoming Meetings
  1. Phase 1-F and 1-G Pre-Phase Meeting – Meeting was held on 07/22/2015. 
 
Schedule

The most current schedule is available below, with active links to all phases. Also included in this schedule are duration of phases, as well as anticipated start and finish dates.

Taxilanes G&L Widening, Phase 1 Schedule

(rev. 07/14/15)

Activity Description Contractor Accessibility to Worksite Duration Anticipated Start Anticipated Finish
Pre-Construction Activities & Dewatering for Phase 1-A 2200 - 0700 / 75 days (for dewatering only) --- Upon Contract Execution 09/17/2014
Phase 1-A  24 hrs / 7 days 116 days 09/18/2014 01/11/2015

Phase 1-B 

24 hrs / 7 days 48 days 01/12/2015 02/28/2015
Phase 1-C 1400 - 0900 / 7 days 176 days 01/12/2015 07/06/2015
Phase 1-D 1400 - 0900 / 7 days 15 days 06/22/2015 07/06/2015
Phase 1-E 1600 - 0900 / 7 days 25 days 07/07/2015 07/31/2015
Phase 1-F 1600 - 0900 / 7 days 45 days 08/01/2015 09/14/2015
Phase 1-G 0700 - 1730 / 7 days 60 days 08/01/2015 09/29/2015
Phase 1-H 0700 - 1730 / 7 days 75 days 09/30/2015 12/13/2015
Box Culvert
(Resumption of work during closure of Taxilane L)
2200 - 0700 / 7 days Concurrent with Phases 1-F through 1-H --- ---
Manuwai Canal Cover
(Resumption of work during closure of Taxilane L)
2200 - 0700 / 7 days Concurrent with Phases 1-F through 1-H --- ---
 
Notes:
  1. There are several phases with overlapping durations. Listed below are phases which must be constructed concurrently, such that the contractor shall have 280 calendar days for construction activities.
    • Phases 1-B & 1-C
    • Phases 1-C & 1-D
    • Phases 1-F & 1-G

Ref. Exhibit No. 2; Widen Taxilanes G and L - Phase 1, Construction Safety Phasing Plan