Aircraft Hardstands at Taxilane 7

Progress

DesignAug 3 2026
ProcurementJun 4 2027
Pre-ConstructionSep 17 2027
ConstructionApr 14 2028
Project Acceptance / PunchlistNov 10 2028

Project Scope

The project will design approximately 28,800 square feet of new aircraft hardstands along Taxilane 7. Environmental services will include all work associated with a Phase II Environmental Site Assessment for the various areas associated with the new Aircraft Hardstands at Taxilane 7 and Terminal 3 at South Ramp projects.

Progress Updates

60% design documents are being prepared.