Daniel K. Inouye International Airport
Honolulu, HI
- Airport Bus Maintenance Facility, HNL - Project No
- AO1143-14
 - Status
- Design
 - Zone
- Ualena Street
 - Milestones
- Planning - Dec 23 2024 - Design - Jun 5 2025 - Procurement - Apr 30 2026 - Pre-Construction - TBD - Construction - Sep 3 2023 - Post-Construction - Feb 3 2028 
 More InfoMore Info
- Parking Structure at Ualena Street at HNL - Project No
- AO1114-20
 - Status
- Procurement
 - Zone
- Ualena Street
 - Milestones
- Request for Proposal - Apr 11 2024 - Procurement - Apr 14 2025 - Pre-Construction - Jan 9 2026 - Construction - Feb 9 2026 - Project Acceptance / Punchlist - TBD - Post-Construction - TBD 
 More InfoMore Info
- Terminal 2 Parking Structure Improvements, HNL - Project No
- AO1114-19
 - Status
- Design
 - Zone
- Terminal 2 Garage
 - Milestones
- Planning - May 1 2024 - Design - Feb 5 2025 - Procurement - Mar 31 2026 - Pre-Construction - TBD - Construction - TBD - Post-Construction - TBD 
 More InfoMore Info
- Concrete Spall Repairs at Terminal 2 Roadways, Daniel K. Inouye International Airport - Project No
- AO1043-33
 - Status
- Construction
 - Zone
- Terminal 2
 - Milestones
- Design - Mar 8 2021 - Procurement - Feb 8 2024 - Pre-Construction - Jul 5 2024 - Construction - Mar 24 2025 - Project Acceptance / Punchlist - Dec 13 2026 - Post-Construction - TBD 
 More InfoMore Info
- Ewa/DH Concourse 2nd/3rd Level Roadways Improvements - Project No
- AO1043-32
 - Status
- Project Acceptance / Punchlist
 - Zone
- Terminal 2
 - Milestones
- Design - Mar 8 2021 - Procurement - Oct 3 2022 - Construction - Jun 1 2023 - Project Acceptance / Punchlist - Jul 30 2025 - Post-Construction - TBD 
 More InfoMore Info
Hilo International Airport
Hilo, HI
- Terminal Infrastructure Improvements, Hilo International Airport - Project No
- AH1042-03
 - Status
- Planning
 - Zone
- Main Terminal
 - Milestones
- Planning - Jul 21 2025 - Procurement - TBD - Pre-Construction - TBD - Construction - TBD - Project Acceptance / Punchlist - TBD - Post-Construction - TBD 
 More InfoMore Info
Ellison Onizuka Kona International Airport at Keāhole
Kalaoa (Kailua-Kona), HI
- Perimeter Fence Replacement, KOA - Project No
- AH2050-09
 - Status
- Post-Construction
 - Zone
- Airfield
 - Milestones
- Design - Oct 29 2018 - Procurement - Mar 4 2022 - Construction - Jul 3 2023 - Post-Construction - Nov 6 2024 - Closeout - Nov 6 2025 
 More InfoMore Info
- Project No
- AH2042-34
 - Status
- Design
 - Zone
- Airport-wide
 - Milestones
- Design - Jun 1 2023 - Procurement - TBD - Pre-Construction - TBD - Construction - TBD - Project Acceptance / Punchlist - TBD - Post-Construction - TBD 
 More InfoMore Info
- Project No
- AH2042-31
 - Status
- Project Acceptance / Punchlist
 - Zone
- Ticketing/Check-in
 - Milestones
- Design - Jul 23 2018 - Procurement - Jan 31 2022 - Construction - Oct 3 2022 - Project Acceptance / Punchlist - Aug 18 2025 - Post-Construction - TBD 
 More InfoMore Info
Lihue Airport
Lihue, HI
- Inline Checked Baggage Belt System, Lihue Airport - Project No
- AK1052-08
 - Status
- Planning
 - Zone
- Baggage Claim
 - Milestones
- Planning - Mar 21 2025 - Design - TBD - Procurement - TBD - Pre-Construction - TBD - Construction - TBD - Project Acceptance / Punchlist - TBD - Post-Construction - TBD 
 More InfoMore Info
- Project No
- AK1045-18
 - Status
- Pre-Construction
 - Zone
- Parking
 - Milestones
- Design - Jul 22 2020 - Procurement - Apr 14 2025 - Pre-Construction - Sep 30 2025 - Construction - Nov 1 2025 - Project Acceptance / Punchlist - TBD - Post-Construction - TBD 
 More InfoMore Info
Kahului Airport
Kahului, HI
- Outbound Baggage Handling System Replacement - Project No
- AM1109-03
 - Status
- Planning
 - Zone
- Main Terminal
 - Milestones
- Planning - Jul 1 2025 - Design - TBD - Procurement - TBD - Construction - TBD - Project Acceptance / Punchlist - TBD - Post-Construction - TBD 
 More InfoMore Info
- Project No
- AM1095-10
 - Status
- Construction
 - Zone
- Main Terminal
 - Milestones
- Design - Sep 22 2021 - Procurement - Jul 26 2023 - Pre-Construction - Mar 4 2024 - Construction - Jun 28 2024 - Project Acceptance / Punchlist - Dec 30 2026 - Post-Construction - TBD 
 More InfoMore Info
- Ticket Lobby Improvements, OGG - Project No
- AM1042-45
 - Status
- Planning
 - Zone
- Ticketing/Check-in
 - Milestones
- Planning - Dec 15 2023 - Design - TBD - Procurement - TBD - Pre-Construction - TBD - Construction - TBD - Project Acceptance / Punchlist - TBD - Post-Construction - TBD 
 More InfoMore Info
- Holdroom and Gate Improvements, OGG - Project No
- AM1042-42
 - Status
- Post-Construction
 - Zone
- Main Terminal
 - Milestones
- Design - May 7 2018 - Procurement - Mar 30 2020 - Construction - May 19 2021 - Post-Construction - Dec 18 2024 - Closeout - Dec 17 2025 