Skip to content

Parking Lot Improvements

Progress

DesignJul 22 2020
ProcurementApr 14 2025
Pre-ConstructionSep 30 2025
ConstructionNov 1 2025
Project Acceptance / PunchlistTBD
Post-ConstructionTBD

Project Scope

Converts an existing employee gravel parking area into a new employee parking lot with asphalt pavement, marked parking stalls, lighting, drainage, installation of electrical and telecommunications infrastructure, and other related improvements.

Also includes improvements to the two existing Bus Shuttle/Transportation Network Companies operation areas, including re-pavement, providing ADA accessible ramps and sidewalks, lighting, and associated infrastructure.

Progress Updates

Construction contract executed.

Pre-Construction activities are on-going.