Progress

PlanningJan 2024
DesignJan 2024
ProcurementMay 2 2025
ConstructionMar 16 2026
Project Acceptance / PunchlistJul 2027
Post-ConstructionTBD

Project Scope

Modifying existing curbside traffic control system and replace with raised concrete speed tables with embedded light flashers at three crosswalks on 3901 Mokulele Loop at Lihue Airport. On either side of each speed table, limited AC pavement will be removed and replaced, providing smooth transitions to the speed tables and positive drainage toward existing catch basins. The removed curb ramps will be replaced with concrete sidewalk to provide a smooth transition to the speed tables, maintaining ADA accessibility through the crosswalks.

Progress Updates

Submittals are in progress.