South TSA Checkpoint, OGG
Progress
DesignSep 22 2021
ProcurementJul 26 2023
Pre-ConstructionMar 4 2024
ConstructionJun 28 2024
Project Acceptance / PunchlistMay 1 2027
Post-ConstructionTBD
Project Scope
Construction of a new security screening checkpoint facility at the south end of the ticket lobby to house multiple TSA screening lanes, enclose the existing security checkpoint and provide air conditioning, and renovate the existing bus terminal canopy.
Progress Updates
The main building structural steel work is complete.
Above ground utility work and wall framing are on-going.
Barricades were construction in Holdroom A of Gate 5 for the new tie-in to the existing holdroom.