Ewa/DH Concourse 2nd/3rd Level Roadways Improvements
Progress
DesignMar 8 2021
ProcurementOct 3 2022
ConstructionJun 1 2023
Project Acceptance / PunchlistMar 31 2025
Post-ConstructionTBD
Project Scope
Repair/replacement of elements along the 2nd and 3rd level roadways of the Ewa and Diamond Head Concourses, including concrete spalling and crack repairs, expansion joint replacement, misc. painting, hazardous material surveys and testing, drain replacement, asphalt repair/replacement, and misc. demolition.
Progress Updates
Construction anticipated to be complete in April 2025.