Outbound Baggage Handling System Replacement

Progress

PlanningJul 1 2025
DesignApr 3 2027
ProcurementSep 27 2027
Pre-ConstructionDec 1 2027
ConstructionJun 1 2028
Project Acceptance / PunchlistJan 30 2030
Post-ConstructionTBD

Project Scope

Terminal renovations to increase baggage handling capacity and compliance with the newest TSA Planning Guidelines and Design Standards. Also includes potential for integrated agricultural inspection equipment, weather proofing the conveyor building, providing an air-conditioned enclosure for the EDS machines, additional lighting and ventilation, and new CBRA and agricultural inspection rooms.

Progress Updates

PDR submitted for review and comment in February 2026.